New Build Snagging Inspections on the Costa Blanca and Costa Cálida: What to Check Before Completion in 2026

New Build Snagging Inspections on the Costa Blanca and Costa Cálida: What to Check Before Completion in 2026

A snagging inspection is a professional walk-through of a newly built home to record every defect — from a cracked tile to a leaking terrace drain — before you sign the completion deed and hand over the balance of the price. On the Costa Blanca and Costa Cálida, where thousands of off-plan apartments and villas complete each year, this single step is the difference between a smooth handover and months of chasing a developer to fix problems you should have flagged on day one. In short: never complete on a new build until you (or a surveyor acting for you) have inspected the property and the developer has agreed a written snagging list.

The good news is that Spanish law is firmly on the buyer's side. Under the Ley de Ordenación de la Edificación (LOE 38/1999), every developer building on the Costa Blanca, Costa Cálida, Costa del Sol or Costa Almería must provide legally mandated guarantees — 1, 3 and 10 years depending on the type of defect. The catch is that these guarantees are far easier to enforce if the defect is documented from the outset. This guide explains exactly what to check, when, and how to protect yourself in 2026.

What is a snagging inspection and why does it matter on the Costas?

"Snagging" (in Spanish, elaborating a lista de repasos or lista de deficiencias) is the process of identifying finishing defects in a new build. It is standard practice in the UK and increasingly expected on Spain's coasts, where a large share of new construction is bought off-plan by international buyers who often cannot visit during the build.

New build stock on the Costa Blanca (Torrevieja, Orihuela Costa, Finestrat, Guardamar) and the Costa Cálida (Mar Menor, San Javier, Águilas) is typically delivered fast and to a competitive price point. Quality is generally good, but volume construction means finishing snags are common: hollow-sounding wall tiles, doors that don't close cleanly, hairline plaster cracks, misaligned kitchen units, poorly sealed shower trays and terrace drainage that pools water. None of these are disasters — but each is far cheaper and quicker to fix while the developer still holds your money.

When does snagging happen in the off-plan process?

Snagging sits right at the end of the off-plan journey, between the developer notifying you that the property is finished and the notary completion. The typical sequence on the Costa Blanca and Costa Cálida is:

  1. Reservation and private purchase contract with staged payments during construction (protected by a bank guarantee — see below).
  2. First Occupation Licence (Licencia de Primera Ocupación / LPO) issued by the town hall. Never complete without it — it confirms the home is legally habitable and lets you connect utilities.
  3. Developer's handover notice — you usually have a short window (often 15–30 days) to complete.
  4. Snagging inspection — ideally in this window, before you sign.
  5. Completion at the notary with the snagging list attached or acknowledged in writing.

If you are still weighing your options, our comparison of off-plan vs resale on the Costa Blanca sets out the trade-offs, and the complete guide to the Costa Blanca covers the wider buying picture.

Should you inspect before or after completion?

Before, whenever possible. Once you have signed and paid, your leverage drops sharply — you are relying on guarantee claims rather than a developer keen to close the sale. Practically, some developers will only give access to a finished unit very close to the completion date, so book your snagging inspector as soon as you receive the handover notice. If the developer refuses a pre-completion inspection, treat that as a red flag and involve your lawyer immediately. A good Spanish property lawyer can insist on inspection access and can hold back completion until agreed snags are dealt with or a retention is put in place.

The new build completion checklist: what to check room by room

A professional snagging surveyor on the Costa Blanca or Costa Cálida typically spends 2–4 hours on an apartment and longer on a villa, testing everything. Here is what a thorough inspection covers.

Documents and legal essentials

  • First Occupation Licence (LPO) issued and valid.
  • Certificado Final de Obra (architect's completion certificate).
  • Energy Performance Certificate (CEE).
  • Libro del Edificio (building manual) and warranties for appliances and installations.
  • Utility connections — water and electricity contracts ready to transfer; confirm the property has a working supply, not just a builder's temporary line.

Interior

  • Tap all wall and floor tiles for hollow sounds and check grouting and levels.
  • Open and close every door and window; check locks, seals, mosquito screens and that nothing sticks.
  • Test every socket, light switch, extractor and the consumer unit (trip the RCD).
  • Run all taps and showers, check hot water, and look for leaks under sinks and around shower trays.
  • Flush toilets and check for silent leaks; check drainage speed.
  • Inspect kitchen units, worktops, sealant and that all included appliances work.
  • Look along walls and ceilings for cracks, damp patches and uneven paintwork.
  • Check air-conditioning pre-installation or units — a key point given Costa summers; see our guide to heating and cooling your Spanish home.

Exterior, terraces and communal areas

  • Pour water on terraces and around drains — it should run away, not pool. Poor terrace falls are the single most common serious defect on Costa Blanca apartments.
  • Check render, exterior paint, balcony railings and glass balustrades.
  • Inspect the pool, garden landscaping and any solarium included in your purchase.
  • Confirm garage/parking space and storeroom match the deed dimensions and boundaries.
  • Note the state of communal areas — these feed into your community fees and are governed by the Horizontal Property Law.

What are the developer guarantees in Spain?

The LOE sets three legally mandatory guarantee periods, running from the date the works are certified as complete. These apply across the Costa Blanca (Comunidad Valenciana), Costa Cálida (Murcia) and Costa del Sol and Costa Almería (Andalucía) — they are national law, not regional.

Legal developer guarantees for new builds in Spain (LOE 38/1999)
Guarantee periodCoversTypical examplesWho is liable
1 yearFinishing and completion defectsCracked tiles, poor paintwork, faulty fittings, misaligned doorsBuilder / contractor
3 yearsHabitability defects in installationsPlumbing leaks, damp, faulty electrics, heating/AC installation, ventilationBuilder and architect/technicians
10 yearsStructural defects affecting stabilityFoundations, load-bearing walls, beams, roof structureDeveloper, architect and builder (backed by insurance)

Most snagging items fall under the 1-year finishing guarantee, which is precisely why a pre-completion inspection matters: you want them logged and fixed inside that window. For the 10-year structural guarantee, the developer must hold a seguro decenal (decennial insurance) — always confirm this exists.

How are your stage payments protected?

Under Spanish law (originally Ley 57/1968, now within the LOE), every euro you pay a developer during construction must be secured by a bank guarantee (aval bancario) or an insurance policy, held in a separate account. If the developer goes bust or fails to deliver, you can reclaim your money plus interest. Before you pay a single instalment on a Costa Blanca or Costa Cálida off-plan purchase, have your lawyer verify these guarantees are genuinely in place. This is one of the strongest legal protections available to off-plan buyers anywhere in Europe.

What does a snagging inspection cost, and who should do it?

On the Costa Blanca and Costa Cálida, independent snagging surveys are widely available and modestly priced compared with the money at stake.

Typical snagging inspection costs on the Costa Blanca and Costa Cálida (2026, guide figures)
ServiceGuide priceNotes
Apartment snagging survey€250–€450Depends on size and location
Villa snagging survey€400–€800+Larger plots, pools and solariums add time
Full structural survey (older/resale)€500–€1,200Usually for resale, not new build
Lawyer attendance at handoverWithin your ~1% legal feeOften included in the conveyancing service

Use an independent surveyor (an arquitecto técnico or specialist snagging company), never the developer's own inspector. Ask for a written, photographed report you can hand to your lawyer. Remember snagging costs are separate from — and small next to — the taxes and fees of buying, which run to roughly 12–15% on top of the price for a new build (10% IVA plus AJD stamp duty of 1.4% in the Comunidad Valenciana and 1.5% in Murcia, plus notary, registry, lawyer and gestoría). Our complete guide to buying taxes in Spain 2026 breaks these down region by region.

What happens if the developer won't fix the snags?

Most reputable Costa developers will remedy an agreed snagging list promptly, because they want a clean completion and a happy client. If they drag their feet, your options are, in order of escalation:

  1. Attach the snagging list to the completion deed or have the developer sign a written commitment with deadlines.
  2. Negotiate a retention — a sum held by the notary or lawyer until snags are fixed. This is your strongest lever and should be arranged before signing.
  3. Formal claim (burofax) through your lawyer citing the relevant LOE guarantee period.
  4. Insurance / court claim for serious 3- or 10-year defects, backed by the decennial insurance.

This is exactly where independent legal representation earns its fee — see why we always recommend using a real estate lawyer, especially as a non-resident buyer.

Regional notes: Costa Blanca, Costa Cálida, Costa del Sol and Costa Almería

The snagging process is the same across all four coasts, but a few local points are worth knowing:

  • Costa Blanca (Comunidad Valenciana): the largest new build market of the four. LPO waiting times at busy town halls such as Orihuela can extend the completion window — don't complete before the licence is issued.
  • Costa Cálida (Murcia): strong villa and Mar Menor development. Check terrace drainage and pool installations carefully given the flat, low-lying terrain. Buy-to-let investors should also review our Costa Cálida and Almería yields guide.
  • Costa del Sol & Costa Almería (Andalucía): premium finishes are more common on the Costa del Sol; snag high-end joinery, home automation and pool systems in detail. Note the lower AJD stamp duty of 1.2% in Andalucía.

Wondering how the coasts compare more broadly? Our four-coast comparison for 2026 is a useful companion read.

Frequently Asked Questions

Do I legally need a snagging inspection to complete in Spain?

No — it is not a legal requirement, but it is strongly recommended. Spanish law gives you generous guarantees, but a documented snagging list makes them far easier to enforce and gets defects fixed while the developer still wants your signature.

Can I complete before the First Occupation Licence is issued?

You should not. Without the Licencia de Primera Ocupación the property is not legally certified as habitable and you may struggle to connect utilities or later sell it. Have your lawyer confirm the LPO before completion.

How long do I have to report new build defects?

Under the LOE, you have 1 year for finishing defects, 3 years for habitability/installation defects and 10 years for structural defects, each running from the completion of the works. You then have a further period (generally two years from discovery) to bring a claim.

Who pays to fix defects found during snagging?

The developer or builder, provided the defects fall within the relevant guarantee period and are properly documented. This is why a written, photographed snagging report is so valuable.

What if I can't attend the inspection in person?

Very common for international buyers. You can appoint an independent snagging surveyor and grant your lawyer power of attorney to represent you at handover and completion. Many Mediter clients complete their entire purchase remotely.

Is snagging different for a villa versus an apartment?

The principles are identical, but villas take longer to inspect and add items such as the pool, garden, boundary walls, solarium and private drainage. Budget for a longer survey accordingly.

Buying a new build on the Costas? Let Mediter guide you to completion

A careful snagging inspection is one of the smartest hours you will spend on your new home. At Mediter Real Estate we help international buyers navigate off-plan and new build purchases across the Costa Blanca, Costa Cálida, Costa del Sol and Costa Almería — from choosing a reputable developer to coordinating your snagging survey, lawyer and completion. Explore our regional guides and contact Mediter Real Estate today to find your ideal new build on the Spanish coast with confidence.